Mizzen Mast replacement on SEA CLOUD II

Mizzen Mast replacement on SEA CLOUD II

 
Gran Canaria, November 2018:
After preparing new mast drawings, partly new standing rigging, crosstree planking and others, the mizzen mast replacement of SEA CLOUD II was successfully carried out at ASTICAN in Las Palmas de Gran Canaria.
 
08. - 16.11. - preparation of the new mast
14. - 16.11. - removing standing rigging and other equipment from the old mast
16.11. - removing the old mast
18.11. - stepping the new mast
21.11. - finish
 
Thanks to our team of 8 riggers and the good preparation of the project, the job was done in time and budget.
 
 